Rainfall intensity must match the risk, catchment and design method rather than a remembered national average.
Select the design basis
State storm duration, return period, climate allowance and data source. Approved Document H gives simplified values for common small situations in England, but higher-risk or larger schemes require the relevant standard and current approval criteria.
Simple flow relationship
A common planning relationship is peak flow = rainfall intensity × effective catchment area, with a runoff factor where the chosen method requires one. Keep units consistent and do not present the result as a complete hydraulic model.
Test more than one duration
Short storms may control inlet flow while longer storms control storage. Check the durations required by the selected method and the downstream discharge limit.
Related guides
Design and compliance boundary
This page provides general UK-oriented learning, not a site design, product approval or statement of legal compliance. Confirm the requirements for the relevant UK nation, planning authority, Lead Local Flood Authority, sewerage undertaker, highway authority and environmental regulator. Use current manufacturer information and competent design. Never enter a chamber, drain or confined space without the required competent system of work.