Irrigation Commissioning Measurement Record

Commissioning proves how the installed system performs. It should compare measured results with the design criteria.

Pump-set pressure gauge with separate bar and psi scales
A pump-set pressure gauge with scales in bar and psi.

Record for every zone

Measurement Reason
Static pressure before start Shows available resting condition.
Running source pressure Shows supply condition at zone flow.
Zone flow Checks demand, leakage and future change.
Critical outlet pressure Confirms residual pressure at the controlling point.
Filter differential pressure Creates clean baseline and identifies restriction.
Start and stop behaviour Checks surge, cycling and control sequence.

Outlet checks

Confirm nozzle or emitter identity, direction, arc, spacing, operating pressure, obvious misting or runoff and physical stability. Where performance criteria require it, complete a suitable distribution or catch-can test.

Control tests

  • Station identification and manual operation.
  • Programme starts, runtimes and seasonal adjustment.
  • Rain, flow, pressure and level sensors.
  • Master valve and pump interlocks.
  • Loss-of-power and communication behaviour.
  • Alarm reporting and safe shutdown.

Compare and resolve

Define tolerances before testing. If results differ, identify whether the cause is the source, pipe, valve, filter, regulator, outlet, control or measurement method. Do not hide an unresolved difference by changing the record.

Copy-and-complete zone test record

Use a separate record for each zone and operating condition. Enter the units and test locations with the readings. Mark an unavailable check as “not tested”, with the reason; a blank or zero must not stand in for a measurement.

System and zone: [controller, station and asset references]
Design reference: [drawing or specification number and revision]
Date and operator: [date, time and person recording the test]
Expected performance: [design flow, required outlet pressure and units]
Acceptance criteria: [documented limits or tolerances agreed before testing, with their source]
Operating conditions: [source level or supply state, other demand, valve positions and filter condition]
Instruments and test points: [instrument references, units, measurement locations and relevant calibration or condition checks]
Measured operating point: [source flow and corresponding running pressure under the same stable conditions]
Other readings: [critical-outlet pressure and filter differential pressure where applicable, with locations and units]
Control observations: [start/stop, sensor and interlock test results, or checks not tested and why]
Outcome: [meets the stated criteria, outside the stated criteria, or not tested]
Outstanding action and retest: [defect, responsible person, action, date and repeat results]

Retain the original readings when recording a correction or retest, and identify the changed revision. A completed record documents the checks performed; it does not replace the technical review or acceptance required for the project.

Related guides

Sources and limitations

This guide supports planning and record keeping. The final design must follow current manufacturer instructions, site risk assessments, legal duties, water-undertaker requirements and applicable standards. Relevant references include HSE HSG47, Water Regs UK backflow guidance and BS EN 805:2025.