Commissioning proves how the installed system behaves under recorded conditions. It is not only a final leak check. Compare the installation with the design and current product instructions, then record any departure.

Before introducing water
- Confirm pipe joints have completed the required cure or installation period.
- Check valve flow direction, accessible isolation and service points.
- Confirm filters, regulators and backflow protection are installed in the intended order.
- Confirm controller, solenoid, cable and field-joint compatibility.
- Open intended flushing points and protect people and property from discharge.
Flush and pressurise
- Flush mains, submains and laterals in a controlled sequence.
- Open the supply gradually to reduce surge risk.
- Close flushing points in the planned order.
- Inspect every accessible joint, valve and component for leakage.
- Clean filters again after the initial flush.
Test each zone
- Operate the valve manually and from the controller.
- Record running pressure and measured zone flow in the commissioning measurement record.
- Compare measured demand with the design allowance.
- Check every outlet for damage, blockage and correct orientation.
- Adjust arcs, radius or flow only within manufacturer instructions.
- Check low points for unwanted drainage after shutdown.
- Confirm dripline flushing, regulation and visible discharge pattern.
Controller and electrical checks
Verify station labels, programme start times, watering days, run times, sensor behaviour and master-valve or pump-start sequencing where used. Test one change at a time. Electrical testing and mains work require suitable competence.
Handover record
- Water source, static pressure and recorded operating points.
- Zone names, valve locations and controller station numbers.
- Pipe, filter, regulator, valve and outlet product codes.
- Controller programme and sensor settings.
- Isolation, flushing, drainage and winter procedures.
- Photographs, product instructions and test results.
- Outstanding defects or departures from the design.
After commissioning
Recheck filters and visible joints after the initial operating period. Update the record when nozzles, run times, valves or pipework change. Use Irrigation Fault Finding if measured performance later differs from the commissioning baseline.
Reference
The sequence is informed by manufacturer installation guidance and the Irrigation Association's field-audit approach. Product-specific instructions and site requirements take priority.
Explore the rainwater section
Explore irrigation water sources
- Choosing an irrigation water source
- Boreholes and wells for irrigation
- Ponds, lakes, rivers and streams
- UK water abstraction rules
- Irrigation water quality testing
- Mains break tanks and alternative water
- Water intakes, screening and pump protection