Irrigation Pressure Testing and Flushing Plan

Do not improvise a test pressure. The procedure must suit the pipe material, component ratings, jointing method, installation stage and applicable standard.

Test plan fields

  • Defined test section and drawing reference.
  • Pipe material, dimensions, SDR or class and component ratings.
  • Jointing method and required curing or cooling time.
  • Test medium, filling method and air-removal points.
  • Specified test pressure, duration and acceptance method.
  • Calibrated instruments and positions.
  • Exclusions, restraints and safe boundaries.

Stored energy

Pressurised systems can fail violently. Exclude people from hazardous positions, secure end caps and temporary fittings, and use a competent test method. Pneumatic testing can carry substantially different risk from water testing and must not be substituted casually.

Air removal

Fill gradually from an appropriate low point and release trapped air through controlled high points where the design permits. Trapped air changes test behaviour and increases stored-energy risk.

Flushing

Plan a route that carries debris out without sending it into valves, regulators, sprinklers or drip emitters. Open branches in a controlled sequence and provide a safe discharge location that will not erode ground, flood property or pollute a watercourse.

Record

Record start and end pressure, time, temperature where relevant, water added, observations, leaks, repairs and retest results. A simple “passed” entry without the test conditions is not auditable.

Related guides

Sources and limitations

This guide supports planning and record keeping. The final design must follow current manufacturer instructions, site risk assessments, legal duties, water-undertaker requirements and applicable standards. Relevant references include HSE HSG47, Water Regs UK backflow guidance and BS EN 805:2025.