Planning an Irrigation Zone

Plan each zone around the water supply and the needs of the outlets that will run together. Adding more outlets without checking flow and pressure can leave the zone unable to water properly.

Three irrigation solenoid valves, control wiring and valve-box components in an open excavation
Three solenoid valves and their wiring in an irrigation valve box.

Planning sequence

  1. Measure dynamic flow and pressure at the intended connection.
  2. Divide the site by plant type, exposure, operating pressure and watering method.
  3. Select the outlet and determine its flow at the intended pressure.
  4. Add the flows for each proposed zone.
  5. Size pipework and calculate likely pressure loss.
  6. Allow for elevation, filtration, control valves and regulation.
  7. Keep future flushing, isolation and maintenance accessible.

Do not mix outlets with very different precipitation rates or pressure needs on one zone. Keep drip irrigation separate from sprays or rotors unless a properly designed arrangement proves otherwise.

Find out how much water is available, which local restrictions apply and what backflow protection the site needs. For design assistance, provide dimensions, levels, water-source readings and the intended planting or turf use.

Measure the supply under flow

Take flow and pressure readings at the proposed connection under a representative discharge. A static gauge reading describes pressure with no demand; it does not establish how much pressure remains at the flow required by the zone.

  • Use a timed-volume test only where the outlet can discharge safely and freely.
  • Record the test location, date, valve position and whether other water uses were operating.
  • If a gauge and controlled test outlet are used together, record pressure and flow at the same operating point.
  • Repeat an unexpected result before using it for design.

Do not exceed the rating of the tap, hose, gauge or fittings. A domestic open-outlet test is a starting measurement, not proof of the capacity of a buried service, water main or pump.

Simple zone worksheet

  • Water source and connection point.
  • Available flow at a stated dynamic pressure.
  • Highest and lowest outlet elevations.
  • Pipe material, actual internal diameter and route length.
  • Outlet model, nozzle, operating pressure and individual flow.
  • Total simultaneous demand.
  • Allowances for pipe, fittings, valves, filters and regulators.
  • Isolation, flushing, drainage and maintenance points.

Check before installation

The proposed zone is not ready merely because the outlet flows add up to less than the bucket-test result. Confirm that adequate pressure remains after elevation and system losses, that the water connection is appropriately protected, and that every component is used within current manufacturer limits.

Group outlets with similar watering needs

A zone should combine outlets with compatible operating pressure, application rate and watering need. Separate turf from planting where their scheduling differs. Separate steep slopes, shaded areas and exposed areas when one run time would create runoff or poor coverage.

Check the most demanding water route

Do not check only the connection point. Identify the outlet with the most difficult combination of elevation, route length, component loss and terminal-pressure requirement. The design must leave adequate operating pressure there at the simultaneous zone flow.

Zone completion test

  • Every outlet has a current flow and operating-pressure record.
  • Total flow is below the measured supply capacity at a stated running pressure.
  • Pipe, valves, filters and regulators have been checked at that flow.
  • Elevation is signed correctly as a gain or loss.
  • Application rates and watering needs are compatible.
  • Isolation, flushing, drainage and servicing are accessible.
  • The finished zone will be measured and observed during commissioning.

Product and SKU references

Match each product to the zone flow, operating pressure, connection size, material and current manufacturer limits, then record its link and SKU. A general product description alone does not show whether the components will work together.

Related Irri Hub guides


Design and field engineering


Soil, plants and irrigation scheduling