Key point: A borehole depth is not its dependable irrigation output. Selection needs a pumping test, water levels, sustainable yield, water analysis and the complete system duty.
Can I get a borehole drilled for irrigation?
Yes. You can commission a specialist water-well drilling contractor to investigate and drill a borehole. Before spending money, establish what water you need, whether groundwater is a realistic option and which permissions apply. Drilling does not guarantee enough usable water.
Start with free nearby borehole records
British Geological Survey borehole records give free access to many scanned borehole, shaft and well logs. Use the linked GeoIndex viewer to look around your site. Records may show drilled depth, the ground layers and their thickness, and water-level observations. Save the record reference and ask your contractor or hydrogeologist to interpret it.
Some logs are for ground investigations rather than water-supply boreholes. Available records do not show every hole. A nearby borehole cannot guarantee the same depth, yield or water quality on your land.
What should I ask a drilling contractor?
- Experience with water-supply boreholes in similar ground.
- Access and working space for the drilling rig.
- Investigation, siting, construction, casing, sanitary sealing, development, test pumping and water analysis, with a professional hydrogeological adviser where appropriate.
- The completion records and test results you will receive.
- Which costs remain payable if usable water is not found.
Ask for a complete supply quotation, separating drilling and tests from the pump, electricity supply, controls, tank, filtration, pipework and commissioning. Commission the drilling and hydrogeological work through suitable specialists; Irrigation Stockist and JK Irrigation’s role here is helping with the connected irrigation equipment after source information is available.
Check permissions before work starts
Use the Environment Agency groundwater investigation guidance for England. Investigation consent and an abstraction licence are separate questions. Confirm proposals at the 20 cubic metre daily boundary with the Environment Agency: its investigation guidance and general abstraction guidance describe that boundary differently. Check landowner permission, planning and test-water discharge. Other UK nations have their own rules.
Can it supply the sprinklers directly?
Compare the tested sustainable source flow with the irrigation system's peak demand. A tank may allow the borehole to fill over a longer period while a separate pump supplies a shorter watering window. Storage does not increase the water available from the ground or the abstraction permitted.
Information to obtain
- Borehole construction and completion record.
- Diameter, total depth and screened interval.
- Static water level before pumping.
- Pumping water level at stated flow and duration.
- Recovery after pumping stops.
- Recommended sustainable yield and any abstraction conditions.
- Water analysis, temperature and sediment information.
Drawdown
Drawdown is the reduction in water level while pumping. It changes the head against which a submersible pump operates. Design for the lowest credible pumping level, while maintaining the pump manufacturer's required submergence, cooling and clearance from sediment.
Do not oversize the pump
A pump capable of more flow than the borehole can sustain can cause excessive drawdown, cycling, sediment movement or loss of water. Controls may require low-level protection, dry-run protection, suitable non-return arrangements and storage so irrigation peak flow is separated from borehole recovery rate.
Recovery rate and irrigation peak are different
A pumping test should establish drawdown and recovery at stated flows and durations. Compare the advised sustainable source rate with the irrigation schedule, not only with one zone's instantaneous flow. If the borehole can provide the required total volume but not the peak irrigation rate, a transfer pump and storage tank may separate borehole recovery from irrigation demand.
That arrangement needs two hydraulic duties: borehole-to-storage and storage-to-irrigation. Check the full storage balance, recovery between cycles, permitted abstraction quantities and periods, treatment, low-level controls and both pump curves. A larger tank cannot fix an unsustainable source or increase an authorised abstraction.
Water quality
Groundwater may contain dissolved minerals even when it appears clear. Iron and manganese can oxidise and create deposits; hardness and alkalinity can affect emitters and treatment; salinity and specific ions can affect plants and soil. Test before specifying filtration or chemical treatment.
England groundwater investigation
Environment Agency investigation guidance requires consent where intended abstraction is 20 m³/day or more. Its general abstraction guidance uses more than 20 m³/day for likely licensing and describes a conditional exemption at 20 m³/day or less. These are separate matters: discuss a proposal at the boundary directly with the Environment Agency before committing to work. Other UK jurisdictions have their own regulators and procedures.
What to send for pump selection
- Borehole and pumping-test report.
- Minimum pumping water level and proposed pump setting.
- Sustainable source flow.
- Required irrigation flow and total dynamic head.
- Rising-main size, length and material.
- Supply voltage, controls and storage arrangement.
- Test method, date, pumping stages/rates/durations, drawdown data and recovery observations.
- Maximum authorised hourly, daily and annual quantities, abstraction period and any monitoring or cessation conditions.
Related Irri Hub guides
- Choosing an irrigation water source
- UK water abstraction rules
- Irrigation water quality testing
- Which irrigation pump do I need?
Sources and limitations
See Environment Agency groundwater investigation guidance and the relevant regulator for the site. A hydrogeological assessment may be required.