The shortest route is not automatically the best route. Balance hydraulic loss, construction risk, maintenance and whole-life access.
Route priorities
- Avoid known utilities, structures, tree conflicts and contaminated ground.
- Reduce unnecessary length, high points and restrictive fittings.
- Provide accessible isolation at logical branches.
- Plan flushing, draining and air management.
- Keep valve boxes away from wheel tracks and recurring standing water where possible.
- Allow for likely future zones or extensions without creating dead legs.
Draw the network before sizing
Number nodes and pipe sections. Record length, flow, material, outside diameter, SDR or class, internal diameter and elevation at each node. This lets an engineer audit the pressure-loss calculation and lets installers identify the intended component.
Crossings
Roads, paths, drainage channels and structures need an agreed crossing detail. Consider sleeves, access, loading, settlement, replacement and whether a failed pipe could undermine the surface.
High and low points
High points can trap air; low points can retain water and be vulnerable to frost or contamination during maintenance. Air valves and drains must be selected and located from an engineering assessment, not added automatically.
Record departures
If site conditions force a route change, update lengths, fittings, levels and hydraulic calculations before covering the work. Mark the final route with measured offsets to permanent features.