Purpose: Collect enough reliable information to design the system once, rather than discovering critical constraints during installation.
Before visiting
- Obtain a current site plan and known utility records.
- Confirm the client, decision-maker and intended users.
- Record the proposed irrigated areas and expected completion date.
- Ask about planning, conservation, landlord or operational restrictions.
Measure on site
| Subject | Record |
|---|---|
| Water | Source, static and running pressure, measured flow, source level and restrictions. |
| Levels | Source, pump, high and low points, critical outlets and major changes in elevation. |
| Ground | Soil texture, drainage, compaction, slope and areas unsuitable for trenching. |
| Use | Planting, turf, sports use, traffic, mowing, public access and watering window. |
| Services | Known electricity, gas, water, drainage, communications and private services. |
| Access | Plant access, storage, road crossings, reinstatement and maintenance routes. |
Photographs and references
Use a repeatable photograph sequence. Include a wide view, the drawing reference, water source, meter or tank, pump position, electrical supply, route constraints and each proposed valve or control location. Do not photograph inside live electrical equipment.
Survey limitations
Mark assumptions separately from measured facts. A desktop drawing, pressure at one unused tap or an unverified utility plan must not be treated as a complete survey.
Related guides
- Design brief and performance criteria
- Pipe route planning
- Trenching and buried services
- Planning an irrigation zone
Sources and limitations
This guide supports planning and record keeping. The final design must follow current manufacturer instructions, site risk assessments, legal duties, water-undertaker requirements and applicable standards. Relevant references include HSE HSG47, Water Regs UK backflow guidance and BS EN 805:2025.