Plan the installation before opening a trench. Work from the design and the current manufacturer instructions, with the right components, safe access and a clear route for future maintenance.
Before work starts
- Confirm water availability, dynamic flow and pressure.
- Identify buried services and obtain necessary permissions.
- Check backflow, potable-water and local water requirements.
- Confirm pipe, fitting, valve, controller and voltage compatibility.
- Plan isolation, drainage, flushing and future maintenance access.
Pipework
Keep pipe interiors clean, support and bed pipe appropriately, use compatible cutting and jointing tools, and observe the manufacturer's insertion depths, tightening guidance and curing times. Never pressure-test solvent-welded systems before the stated cure period.
Valves, filters and regulators
Follow flow arrows. Provide access for cleaning, adjustment and replacement. Flush upstream pipework before connecting small waterways. Fit filtration and regulation according to the most sensitive downstream equipment.
Sprinklers and dripline
Install outlets to the design spacing and operating pressure. Keep different watering methods on suitable separate zones. Provide dripline flushing points and use air or vacuum management where the design and manufacturer require it.
Electrical equipment
Use the specified voltage, cable, joints and protection. Mains electrical work and any work beyond your competence must be completed by a suitably qualified person.
Commissioning
- Flush pipework and laterals.
- Open the supply gradually.
- Check every joint and valve for leakage.
- Measure operating pressure and zone flow.
- Adjust outlets according to their instructions.
- Record controller settings and product locations.
- Explain isolation, cleaning and winter procedures to the operator.
For component selection, visit Product Selection. For a problem, visit Fault Finding.
Water connection and backflow protection
A fixed irrigation system can present a backflow risk to a mains water supply. The required protection depends on the downstream fluid category, how the system is used and the installation arrangement. Fertiliser or chemical injection, submerged hoses, below-ground outlets and permanently connected equipment can change the risk.
Water Regs UK states that hose-union taps supplying watering systems are commonly assessed as fluid category 3 or 5 and that irrigation installations may require notification. Confirm the required arrangement with the local water undertaker before installation. A trigger nozzle, ordinary isolation valve or generic non-return valve must not be assumed to provide adequate protection.
Valve and control checks
- Confirm the valve flow direction and accessible servicing position.
- Flush the upstream route before allowing debris into small valve ports.
- Match solenoid voltage and type to the controller output.
- Use cable and field connections specified for the environment.
- Label each station wire and valve before burial or enclosure.
- Test manual operation and controller operation separately.
Commissioning record
Record the water-source reading, running pressure, measured zone flow, controller programme, valve locations, filter and regulator details, outlet settings and any departure from the design. Photograph accessible equipment and retain product instructions. These records help with later maintenance and fault finding.
Electrical and service-identification guidance
Design and field engineering
- Irrigation site survey checklist
- Design brief and performance criteria
- Calculate irrigation zone flow
- Critical-path hydraulic check
- Irrigation design review checklist
- Commissioning measurement record
- As-fitted drawings and handover