Safety first: Never begin excavation from an irrigation drawing alone.
HSE’s three-part approach
HSG47 describes three basic elements for safe work near underground services: plan the work, locate and identify buried services, and excavate safely.
Before excavation
- Obtain current service information from owners and the site.
- Walk the route and identify signs of unrecorded services.
- Use suitable locating equipment and competent operators.
- Mark the agreed route and trial-hole strategy.
- Define exclusions, supervision and emergency actions.
- Review changes when site evidence conflicts with records.
Private services
Sports grounds, estates and commercial sites often contain private lighting, irrigation, drainage, fuel, data or power routes absent from statutory plans. Speak to people with site knowledge but verify rather than relying on recollection.
Trench design
Specify bedding, cover, separation, marker systems, crossings and reinstatement for the pipe, cable, loading and ground. Protect pipes from sharp objects, point loads and unacceptable settlement. Keep spoil and plant movements controlled.
Open-trench quality check
- Confirm route, depth and crossings.
- Photograph and measure changes.
- Inspect pipe and cable for damage.
- Check joints and thrust requirements.
- Complete required tests before covering.
- Update the as-fitted record.
Related guides
Sources and limitations
This guide supports planning and record keeping. The final design must follow current manufacturer instructions, site risk assessments, legal duties, water-undertaker requirements and applicable standards. Relevant references include HSE HSG47, Water Regs UK backflow guidance and BS EN 805:2025.