How to Identify and Label Irrigation and Water Pipework

Key rule: Pipe colour is a clue, not proof. Identify the complete service from its markings, source, destination, records and competent checks before cutting, connecting or ordering parts.

Several black pipe runs and fittings exposed in an open excavation before backfill
JK Irrigation photograph: several black pipe runs and fittings visible in open excavations before backfill. Appearance alone does not establish the service, pipe material, diameter, pressure class or flow direction; record markings, measurements and routes while they are accessible.

Why labels matter

Irrigation sites can contain potable mains water, harvested rainwater, borehole water, chemical or fertiliser dosing routes, fire systems and abandoned pipework. Incorrect identification can create contamination, flooding, pressure and safety risks.

A practical identification record

  1. Photograph the pipe body, stripes and complete printed marking.
  2. Measure the outside diameter in millimetres.
  3. Record where the service begins and ends.
  4. Record the water source and intended use.
  5. Identify valves, pumps, tanks, filters and backflow protection on the route.
  6. Mark direction of flow where it is not obvious.
  7. Update the site drawing and valve schedule.

Visible pipe-service marking

Water Regs UK summarises BS 1710 principles for water services. It describes a green basic identifier for water, with additional code or safety colours to show source and water quality. It also calls for visible identifiers at important positions such as junctions, valves and wall penetrations, with supplementary information and flow direction where needed.

This is not the same as assuming that the manufactured colour of a buried PE pipe fully identifies the installed service. Apply appropriate permanent labels and records to the complete system.

Non-potable irrigation water

Harvested rainwater and other alternative supplies should be clearly identified as non-potable wherever confusion is possible. Labelling must remain legible through maintenance and alteration. Do not create a direct or removable cross-connection to a wholesome-water system.

Before cutting an unknown pipe

  • Do not rely on colour, position or an old drawing alone.
  • Trace and isolate the route using an agreed safe method.
  • Consider stored pressure and automatic pump starts.
  • Confirm the contents and any contamination risk.
  • Use a competent person where the service cannot be positively identified.

Handover information

  • As-fitted plan and pipe schedule.
  • Source and water-quality description.
  • Valve and isolation locations.
  • Pipe material, diameter, SDR and pressure information.
  • Labels, flow arrows and buried marker positions.
  • Inspection and maintenance responsibility.

Related Irri Hub guides

Sources and limitations

See Water Regs UK pipe-identification guidance. It is a summary of BS 1710:2014 and states that it is informative, non-statutory guidance. Use the full applicable standards, regulations, water-undertaker requirements and project specification.