Maintenance frequency should follow risk, duty and observed condition. A fixed calendar may miss the needs of a dirty-water system or lead to unnecessary work on a clean, lightly used system.
Operator checks
- Unexpected water use, leakage or wet areas.
- Abnormal pump noise, vibration, heat or cycling.
- Controller alarms and sensor status.
- Outlet damage, blockage, runoff or poor coverage.
- Source level and visible water-quality change.
Measured condition
Use baseline values from commissioning. Trend zone flow, running pressure, filter differential pressure and pump performance. A gradual change can prompt investigation of blockage, leakage, wear or source deterioration; it does not establish the cause by itself.
Operating hours and event history
Where a controller provides an operating-hours counter or event history, retain a dated reading alongside the system state and measured conditions. Increasing hours can help plan maintenance and compare duty over time; hours alone do not establish pump condition. Pair them with flow, running pressure, start counts, alarms and observations of noise, vibration or cycling. Record speed or electrical readings only where the installed controls provide them or a competent person can obtain them safely.
Seasonal tasks
| Stage | Typical controlled work |
|---|---|
| Pre-season | Inspect source, start gradually, flush, clean filters, test zones and confirm programmes. |
| Operating season | Monitor performance, clean by condition, correct damage and review watering need. |
| End of season | Record condition, isolate as designed, drain or protect vulnerable equipment and secure controls. |
Safety and competence
Separate operator checks from tasks requiring pressure release, electrical isolation, confined-space controls, chemical handling or specialist competence.
Spares and product records
Keep nozzle, solenoid, diaphragm, filter-element and seal references for critical equipment. Match each SKU to the installed model and compatible replacement part.
Related guides
- Spring recommissioning checklist
- Seasonal shutdown and restart
- Fault evidence record
- As-fitted records
Sources and limitations
This guide supports planning and record keeping. The final design must follow current manufacturer instructions, site risk assessments, legal duties, water-undertaker requirements and applicable standards. Relevant references include HSE HSG47, Water Regs UK backflow guidance and BS EN 805:2025.